Development of detailed design HV combined heating and power plant (food industry).
A detailed substation earthing study was previously completed on site, requiring close co-operation with a regional DNO (District Network Operator) – as a result of a unique connection configuration.
PTSG Specialist Earthing and Power was contracted to develop an earthing solution for the new build CHP plant. The installation work was undertaken by a third party, with the design development requiring co-operation with other professionals.
The design was completed ensuring that both industry- and client-specific requirements were adhered to. The final testing, commissioning and certification of a compliant installation were also undertaken by PTSG.
The design documentation was produced working in collaboration with others and enabled a safe, cost-effective and deliverable solution to be achieved.